Sep 2, 2025

Brownsville South Construction Progress: 609 Osborn

August 28, 2025

Side walks have been poured, scaffolding removed, and brick work is complete.  



August 07, 2025: 


Exterior construction of 609 Osborn, one of three buildings part of our Brownsville Crossing project, is close to completion. 



Interior construction is in process. Metal framing studs have being added to the interior of the walls, while the insulation and ducts are exposed, soon to be covered with drywall. 














June 10, 2024:

Shoring and excavation has begun at 609 Osborn, one of three buildings under construction as part of our Brownsville Crossing project.